UF-256 - Counseling and Wellness Center
Building Number: 0081 - STUDENT HEALTHCARE FACILITY
Project Description: Project to provide approximately 20,000 GSF new facility and master planning for complete build-out
Project Manager: Scott Whiddon
Standby PM: Carol Walker
Architect: Ponikvar & Associates
Contractor: Charles Perry Construction, Inc.
Final Completion Date: FEBRUARY 2010
Status: Construction proceeding - 60%
Infirmary History Presentation
Aerial Photos
Current Rendering
Project Schedule